Lake Manatee Dam Rehabilitation Project is a Go

Published Friday, April 4, 2014 12:07 am

BRADENTON -- The Lake Manatee Dam is approaching 50 years old, and recent inspections reflect more damage then was previously thought after leaks were discovered earlier this year. The repair cost could reach $15 million on just the first phase, and it is crucial that the first segment of the work is finished before summer rains fall. 

 

It was during an annual inspection that the initial concerns were discovered, and further examination revealed even deeper problems.

 

Coring tests identified voids under the downstream spillway, and loose soils near the walls; classifying the dam as "stressed." To minimize problematic effects, the county lowered the lake from 40 feet, to 38 feet.

 

Additional field work and core samples revealed design structures not acceptable under today's standards.  

 

Repair plans have been broken into Phase 1-A, and Phase 1-B. Phase 1-A will reestablish seepage control and a new cutoff wall. The cutoff wall will be extended an additional 750 feet south and 1,700 feet north. Phase 1-A needs to be completed before the summer rains get heavy, and will cost $8.6 million. 

 

Phase 1-B includes a new cutoff wall and will be extended to near the dam abutments. Phase 1-B is lower priority and can be done during the rainy season, at a cost of $5.5 million; add the engineering cost to both projects and the projects comes to, $14,091,190. 

 

The emergency agreement approved at Thursday's BOCC Land Use meeting was executed by Manatee County Administrator Ed Hunzeker.

 

BOCC members also approved Budget Amendment B-14-049, appropriating $15,100,000 for phase 1-A and 1-B of the project. 

 

Funds for the project will come from Utility Systems Reserves, and long-term financing for the project will be considered in the five-year Capital Improvement Program as part of the upcoming budget.

 

Commissioner DiSabatino questioned the need to invoke the Emergency Agreement (making it a no bid contract). County Attorney Mickey Palmer told DiSabatino that because of the rain and the safety issues, "It makes this a perfectly suitable emergency example."

 

The Tampa-based company doing the work is Hayward Baker, which has experience with the issues facing the dam. 

 

Work for Phase 1-A is scheduled to be done in June of 2014, and sometime in October of this year for Phase 1-B. 

 

Aerial view of Lake Manatee from NOAA
https://www.thebradentontimes.com/clientuploads/Environmental/manateedam550.jpg

Join the conversation post Facebook comments here or on our site at the bottom of article.

 

  In Addition to Facebook Comments You Can Also Post Comments Below



Non-Facebook Comments:

Click here to add a Non-Facebook comment to this page




 Sign up for our free news subscription - a great way to stay informed!



News World Round UpSports Roundup

Manatee Rural Health Certificate
 


Obituaries

Name Date
David Rojas October 24, 2014
Monique Staves October 27, 2014
Patricia Gandley October 28, 2014
John Dean October 26, 2014
Viola Heckendorn October 25, 2014
Dennis Sabo October 25, 2014
Donald Smith October 25, 2014
James Powers October 22, 2004
Daniel Siglin October 21, 2014
All Obituaries






Copyright © 2009 - 2014 | The Bradenton Times | More than just an Online Newspaper | http://www.thebradentontimes.com/
405 26 Avenue Bradenton, FL 34205
Phone: 941-896-7857 - Privacy Policy - RSS Feed
Template provided by Free CSS Templates